On July 13, 2024, a massive wind turbine blade snapped off at the Vineyard Wind 1 project off the coast of Massachusetts. The 107-meter GE Vernova Haliade-X blade broke about 20 meters from its base. A large piece sank to the ocean floor. The break scattered thousands of pieces of fiberglass, foam, and other debris into the ocean and onto Nantucket’s beaches. It happened during peak summer tourist season, which made the damage worse for local businesses.
A 107-meter wind turbine blade snapped off Nantucket’s coast, scattering debris across beaches during peak tourist season.
Investigators traced the cause to a manufacturing defect at LM Wind‘s facility in Gaspé, Quebec. The blade’s internal materials weren’t bonded properly, and quality control didn’t catch the flaw. GE Vernova later removed and replaced the defective blades already installed at the project. Other blades made at the same Quebec facility were also flagged as potentially affected.
The Bureau of Safety and Environmental Enforcement, known as BSEE, ordered the 804-megawatt project to shut down after the incident. The suspension was later amended, allowing some activities to resume under conditions. GE Vernova and Vineyard Wind were required to remove numerous defective blades from the site. As of mid-2025, BSEE hadn’t finished its independent investigation and hadn’t released any public findings. BSEE launched an inquiry into the blade failure but has not publicly confirmed details of its findings to date.
Debris kept washing ashore for several months, requiring extensive cleanup. On July 11, 2025, Nantucket reached a $10.5 million settlement with GE Vernova. The deal set up a community claims fund to cover cleanup costs and business losses tied to the blade failure. An independent third-party administrator was hired to review and pay out claims. By some accounts, the $10.5 million is a relatively small amount compared to GE Vernova’s increase in market value since the incident.
The settlement released Vineyard Wind and its related companies from further claims tied to this event. However, the settlement releases Vineyard Wind and related companies even though Vineyard Wind itself was not the primary settling party. Some officials and residents criticized what they saw as a lack of leadership, accountability, and transparency from the company. The agreement doesn’t cover future blade incidents or unrelated events. Individuals and businesses that file claims can still pursue separate claims for any unrelated incidents. Some local critics, including ACK For Whales, described the deal as a “sweetheart deal” that failed to hold Vineyard Wind and GE Vernova adequately accountable.
References
- https://www.workboat.com/wind/nantucket-settles-with-ge-vernova-for-vineyard-wind-blade-failure
- https://vineyardgazette.com/news/2025/07/10/vineyard-wind-blade-break-reverberates-one-year-later
- https://www.windtech-international.com/projects-and-contracts/nantucket-and-ge-vernova-reach-settlement-over-vineyard-wind-blade-failure
- https://nantucketcurrent.com/news/one-year-later-vineyard-wind-blade-failure-still-unfolding
- https://www.nantucket-ma.gov/3655/Nantuckets-Settlement-with-GE-Vernova
- https://www.offshorewind.biz/2025/01/21/canada-made-ge-vernova-blades-to-be-removed-from-vineyard-wind-1-site/
- https://newbedfordlight.org/vineyard-wind-completes-installation/