Maryland electricity customers are paying far more for power than they did 15 years ago, and data centers may be a big reason why. Transmission rates for Maryland utilities like Pepco, BGE, and Delmarva Power & Light have jumped five to six times since 2010. Average residential electricity prices rose approximately 18% between 2024 and 2025 alone.
Transmission rates for Maryland utilities have jumped five to six times since 2010 — and data centers may be driving the surge.
Maryland customers have been assigned $7.1 billion in transmission capital costs from 2010 to 2030. Another $5.4 billion is expected from 2031 to 2035. Much of that spending reportedly ties directly to data center growth happening mostly outside Maryland’s borders.
Data centers in Virginia and Ohio are the main drivers behind rising transmission costs across the PJM region, which manages electricity for 13 states including Maryland. PJM forecasts 42% peak demand growth region-wide, but only 12% in Maryland. Still, Maryland’s customers are paying 10% of PJM’s baseline transmission projects in 2029, and 8% in 2030, even though the state accounts for just 2% of regional load growth.
Over $2.2 billion of PJM’s $24 billion in baseline projects have been assigned to Maryland customers, despite most data center expansion happening elsewhere. Data center demand is expected to add roughly 32 gigawatts across PJM by 2030. That’s a massive amount of new power demand, and Maryland ratepayers are helping foot the bill. This growing demand surge stands in stark contrast to the broader energy transition, where costs for solar and wind have plummeted and renewables are projected to meet an estimated 95% of electricity needs by 2050.
Local transmission projects add more costs on top of that. Capital spending on local projects totals $2.8 billion from 2010 to 2030, with another $2.2 billion projected through 2035. Critics say these local projects avoid serious regulatory review. BGE even requested incentives for $634 million in transmission projects tied to Virginia data center reliability.
Utility spending is also set to spike. Exelon reportedly plans $6.48 billion in transmission spending for Pepco, BGE, and Delmarva from 2026 to 2028. That’s nearly three times what was spent from 2023 to 2025.
Maryland’s Office of People’s Counsel has challenged several PJM cost assignments and filed complaints about regulatory gaps. Baseline projects cost approximately four times more than competitively procured projects, highlighting the financial impact of exempting them from competitive procurement. Governor Moore has also reportedly criticized PJM’s processes as energy costs across the region have climbed 23% to 40% over five years. Adding further strain, two Baltimore-area fossil fuel plants scheduled for retirement in 2025 must remain operational until 2029, costing consumers $629 million to prevent blackouts while the region struggles to integrate new generation resources.
References
- https://moderatelymoco.com/electric-transmission-costs-have-soared-for-maryland-customers-and-will-grow-much-faster-in-coming-years-new-opc-report-shows/
- https://opc.maryland.gov/Portals/0/Files/Publications/Rising Transmission Costs 2026-03-19 FINAL.pdf?ver=9alXOSTVPsoktFHyhebZug==
- https://www.energycentral.com/energy-management/post/news-as-data-centers-multiply-maryland-s-power-grid-struggles-to-keep-up-DHBAmhlVr9OHQRC
- https://www.govtech.com/products/maryland-lawmakers-address-cost-of-data-center-surge
- https://www.pecva.org/resources/publications/piedmont-view/call-for-state-action-on-data-centers-gets-louder/