A new kind of geothermal power plant in Geretsried, Bavaria, has started delivering electricity to the German grid. The project, built by the Canadian company Eavor, went live on December 4, 2025. It’s the world’s first commercial closed-loop geothermal plant to send power to a public grid.
The plant uses a system called the Eavor-Loop. It works by circulating a sealed fluid through two deep vertical wells connected by long horizontal tunnels underground. The fluid absorbs heat from the surrounding rock and carries it back to the surface. From there, the heat powers turbines that generate electricity. No fracking, no aquifers, and no open fluid contact with rock formations are needed.
Each well pair has roughly 16 kilometers of continuous wellbore, making them among the longest in the world. The fluid moves on its own because warm fluid is lighter than cool fluid. This density difference keeps it flowing without constant pumping.
The plant can produce 64 megawatts of thermal energy and 8.2 megawatts of electricity. That’s enough to heat approximately around 20,000 homes. It’s also expected to cut carbon emissions by up to an estimated 44,000 tons per year.
Right now, only one of four planned loops is running, producing reportedly around 0.5 megawatts. The team’s working to bring the other three loops online. The horizontal laterals are permanently sealed from surrounding rock using Rock-Pipe technology, which prevents fluid interaction with underground formations and eliminates induced-seismicity risks.
Construction started in October 2022, and drilling began in July 2023. The on-site power plant was finished in late 2024. The project ended up costing more than the original estimate of €200 to €350 million. Eavor hasn’t released the final figure, but reports suggest it reportedly exceeded €300 million. The project has attracted backing from a broad range of investors, including bp Ventures and Temasek, among many others.
The site was originally abandoned as a conventional geothermal project because the rock was hot but too dry and hard to use with traditional methods. The Eavor-Loop solved that problem by not needing permeable rock at all. Unlike traditional hydrothermal geothermal plants, closed-loop systems like the Eavor-Loop are designed to access heat virtually anywhere on the planet.
Eavor’s goal is to reach 150 megawatts of electrical capacity by 2030. The company says the technology can work in many places around the world, not just areas with traditional geothermal activity.
References
- https://www.powermag.com/eavors-first-of-its-kind-closed-loop-geothermal-project-produces-grid-power-in-germany/
- https://mliebreich.substack.com/p/big-news-closed-loop-geothermal-delivers
- https://cleantechnica.com/2026/01/15/when-next-generation-geothermal-meets-first-of-a-kind-reality/
- https://eavor.com/press-releases/eavor-technologies-achieves-first-electricity-production-at-geretsried-site/
- https://eavor.com/blog/eavors-first-of-its-kind-closed-loop-geothermal-project-produces-grid-power-in-germany/
- https://eavor.com/blog/new-geothermal-technology-aims-to-produce-clean-energy-in-germany/
- https://knowledge.energyinst.org/new-energy-world/article?id=140011
- https://www.geodrillinginternational.com/geothermal/news-articles/4528465/investors-look-geretsried-eavor-loop-success-interest