The global gas turbine industry‘s got a serious problem. Orders are piling up fast, but factories can’t keep up. Buyers are now waiting nearly five years to get their turbines. And for orders placed today, the wait could stretch to seven years.
Demand exploded in 2025. Data centers, power companies, and factories all rushed to lock in gas turbines. GE Vernova’s backlog hit 83 GW by the end of 2025 and could potentially reach 100 GW in 2026. Siemens Energy reported a record €136 billion backlog after reportedly selling 194 gas turbines in 2025, nearly double its 2024 total. Mitsubishi Power is sold out through 2028.
Only three major companies make heavy-duty gas turbines. GE Vernova, Siemens Energy, and Mitsubishi Heavy Industries control the entire market. Together, their market caps total roughly $337 billion. But even with that financial muscle, they can’t build turbines fast enough. Production is still running an estimated 20-25% below what buyers need.
The supply chain’s making things worse. Key parts like high-temperature blades come from just a few suppliers, including Howmet Aerospace and Precision Castparts. Forged rotors are made at only a handful of plants worldwide, including Japan Steel Works in Japan. Transformers, steam generators, and control systems are all backlogged too. Skilled workers are also hard to find.
The U.S. is a big part of why demand’s so high. Gas power under construction topped 29 GW by January 2026, double the year before. According to industry reports, pre-construction projects reached 159 GW. Data centers are driving much of that growth.
Manufacturers are cautious about ramping up too fast. They’ve been burned before. In the early 2000s, too many turbines got built. Then the 2008 financial crash hit. Orders dried up again around 2018, helping push GE to eventually spin off GE Vernova. Those painful memories are making companies think twice before spending big on new factories.
Even with some expansion planned, experts say wait times won’t improve much before 2027. And new capacity from those efforts likely won’t show up until after 2030. Siemens Energy has committed to a $1 billion investment in U.S. production of grid and gas turbine equipment, including facility upgrades and the creation of over 1,500 skilled roles.
Some buyers are turning to the secondary market, with developers now sourcing refurbished 1990s turbines due to the unavailability of new units, while large industrial conglomerates are purchasing units on spec just to guarantee future equipment access.
References
- https://gasturbinehub.com/oems-recovered-market-responded-what-2025-tells-us-about-gas-turbines-in-2026/
- https://www.primary.vc/articles/the-gas-turbine-bottleneck-reshaping-energy-infrastructure-ex8qe
- https://oilprice.com/Energy/Energy-General/US-Power-Boom-Triggers-Global-Gas-Turbine-Shortage.html
- https://energynewsbeat.co/gas-turbines-suffer-economic-hardships-due-to-stress-placed-on-them-by-wind-and-solar/
- https://www.woodmac.com/blogs/energy-pulse/supply-chain-constraints-limit-the-growth-of-gas/
- https://thinc.blog/2025/09/07/gas-turbine-manufacturers-gun-shy-about-increasing-production/
- https://heatmap.news/ideas/natural-gas-turbine-crisis